Ottawa is refusing to flinch after Ontario Power Generation admitted that the first reactor at its Darlington small modular reactor site will miss its $7.7-billion budget and may slip by at least a year, with federal Energy Minister Tim Hodgson dismissing the setback as “a reality in all first-of-a-kind projects.”
The admission, buried in quarterly financial statements released on Tuesday, marks the first serious engineering and cost wobble for a project that has become a showcase for Canada’s nuclear ambitions — and for the federal government’s willingness to put taxpayer-backed capital behind them.
Hodgson holds the line as costs slip
Hodgson defended the Canada Growth Fund’s $2-billion equity investment in the Darlington New Nuclear Project, arguing that the fund exists precisely to absorb risk in technologies that could drive economic growth and help meet climate goals.
“It’s important for Canada that we do not balk on making these important investments,” he said.
His comments came after OPG said it would undertake a comprehensive assessment following filings with the Ontario Energy Board that pointed to cost overruns and delays. The Crown corporation attributed the overruns to the “ongoing engineering” work of its partner, GE Vernova Hitachi Nuclear Energy, which is responsible for designing the BWRX-300 reactor and other parts of the facility.
GE Vernova Hitachi spokesperson Jonathan Allen pushed back at the suggestion that his company bore sole responsibility. “While engineering and design maturity are important considerations, as OPG’s update recognizes, there are multiple interconnected contributions across engineering, procurement and construction, as well as evolving market conditions, including inflation and geopolitical risks.”
OPG did not put a figure on the overrun or spell out the full extent of the delay. But a production forecast included in the filing suggests the project’s timing could slip by at least a year. The utility had previously targeted an in-service date of October 2030. The delay could ultimately prove shorter than a year, depending on the outcome of an assessment expected to be completed by mid-2027.
The Darlington New Nuclear Project has a total budget of $20.9-billion and involves building four BWRX-300 reactors and accompanying infrastructure next to the existing generating station in Clarington, Ontario.
The $2-billion question for taxpayers
The project was among the first to be shepherded through the Major Projects Office last year and later received significant equity commitments from the federal and provincial governments through the Canada Growth Fund and the Building Ontario Fund.

Mathieu St-Amand, a spokesperson for the Canada Growth Fund, said in an email that “the equity commitment is being deployed over time.” A corporate presentation from the fund states that the investment is subject to certain conditions, but St-Amand declined to say whether those conditions were tied to specific project timelines or cost estimates.
Another CGF presentation says the fund’s capital will be deployed in two tranches: one tied to the first reactor unit and another for the remaining three units, contingent on the achievement of certain milestones.
Asked whether the investment remained a prudent use of public funds, Hodgson said every project has contingencies built in. “There are on and off ramps for the CGF to be involved, and I’m confident that it is well structured project-to-project to protect the CGF,” he said.
That may reassure ministers, but it will not quiet critics who see the Darlington project as an expensive experiment. Pierre-Olivier Pineau, chair in energy sector management at HEC Montréal, said the challenges “underscore the fact that we need to be very cautious and honest in our energy and electricity policy across Canada.”
He argued that governments should take their time before committing any further money. “We should never think because we’ve invested so much, we should keep investing,” he said, describing the initial costs as already more than anyone would ever want to pay for electricity. “If they add more billions to this already expensive experiment, then we definitely can take a few more years to think about it.”
A global showcase with a domestic timetable
The Darlington project is being watched closely around the world because it is the first small modular reactor to begin construction in a Group of Seven country. There are also proposals to build BWRX-300s in several other countries, including the United States, Britain and Poland.
In the US, GE Vernova Hitachi has partnered with the Tennessee Valley Authority to build the first single BWRX-300 on American soil at its Clinch River site. Although no construction date has been announced, the US Nuclear Regulatory Commission recently issued a construction licence for that project.
“It would be premature to speculate on any direct impact to TVA’s potential projects,” TVA spokesperson Elizabeth O’Connor said in a statement. “TVA remains committed to a disciplined approach to deploying advanced nuclear technology and will continue working through partnerships to ensure costs are managed responsibly to protect TVA customers.”
In Ontario, the Independent Electricity System Operator did not respond directly to questions about how the Darlington delays might affect plans